How it works: count good parts with GOOD +1 (or the Space bar — a USB clicker or foot pedal works too), S logs scrap, D opens the downtime reasons. Breaks go on Planned Stop so they don't hurt availability.
Shift setup
Set these before the shift starts — you can change them at any time and the board updates immediately.
How OEE is figured: Planned production time = shift elapsed − planned-stop time. Availability = run time ÷ planned production time. Performance = (ideal cycle time × total count) ÷ run time. Quality = good ÷ total count. OEE = Availability × Performance × Quality.
Counting from a clicker: plug in any USB clicker or foot pedal that sends the space bar — each press counts one good part while the board is on screen.
Shift reports
Everything below comes from this shift's own entries on this device.
Downtime Pareto
Event log
End of shift
Ending the shift shows the final summary, then clears counts, times, and the log so the next shift starts clean. Setup values are kept.